Past Projects
Santa Rosa Memorial Hospital Medical Building
12/19-5/20


SRMH Medical Building
The SRMH Medical Building project consists of trenching & backfill for plumbing, electrical & gas.
Project Characteristics
Private Work
Final Contract $165,000
Owner: Santa Rosa Memorial Hospital
General Contractors: Indoor Environmental Services & Rex Moore
SRJC Petaluma Campus Building
6/19-10-20

SRJC Petaluma Campus Science Building
The SRJC Petaluma Campus project consists of demolition, grading, paving, storm drain, water main & sewer work on the SRJC Petaluma campus for infrastructure to a science building and parking area.
Project Characteristics
Public Work
Final Contract Amount $717,000
Owner: Santa Rosa Jr. College
General Contractor: JL Modular/Construction
Healdsburg High School Gymnasium & Locker Room
6/19-9/20


HHS Gymnasium
& Locker Room
The Healdsburg High School project consists of demolition, grading, paving, storm drain, water main & sewer work on the Healdsburg High School campus in Healdsburg for their new gymnasium.
Project Characteristics
Public Work
Final Contract Amount $2,029,000
Owner: Cotati-Rohnert Park Unified School District
General Contractor: Lathrop Construction
Carole Sauers Building 2019
10/19-9/20
Carole Sauers Building 2019
The Carole Sauers project consists of demolition, grading, paving and underground utilities for a new building.
Project Characteristics
Private Work
Final Contract Amount $458,200
Owner: Carole Sauers
General Contractors: Eddinger Enterprises

SVHS Culinary Arts Modernization
6/20-11/20
SVHS Culinary Arts
Modernization
The Sonoma Valley High School project consists of demolition, grading & storm drain for a new ADA entrance to the Gymnasium.
Project Characteristics
Public Work
Final Contract Amount $417,000
Owner: Sonoma Valley Unified School District
General Contractor: GCCI


.png)
NVUSD Modernizations
6/20-9/20
NVUSD
Modernization
The NVUSD Modernization project consists of demolition, grading & paving for a new ADA improvements.
Project Characteristics
Public Work
Final Contract Amount $491,000
Owner: Napa Valley Unified School District
General Contractor: Wright Contracting




Caltrans OQ7004
Emergency Culvert Replacement
4/20-10/20
Caltrans OQ7004
The Caltrans 04-2Q9504 is an emergency project consisting of replacing a failed culvert on Highway 1 near Jenner.
Project Characteristics
Public Work
Final Contract Amount: $172,000
Owner: Caltrans
Finishing Kitchens
1/20-4/20


Finishing Kitchens
The Finishing Kitchens project consists of demolition, grading, paving, & sewer work on the Vichy Elementary & Browns Valley Elementary School Campuses for new school Kitchens & ADA improvements.
Project Characteristics
Public Work
Final Contract Amount: $256,000
Owner: Napa Valley Unified School District
General Contractor: Arntz Builders
Caltrans 04-4Q4104
Emergency Slide Repair
9/19-3/20
Caltrans 04-4Q4104
The Caltrans 04-4Q4104 is an emergency project consisting of the installation of a sheet pile wall, rock slope protection, storm drainage, paving & striping.
Project Characteristics
Public Work
Final Contract Amount: $428,000
Owner: Caltrans
.png)
Technology High School
1/19-12/19

Technology High School
The Technology High School project consists of demolition, grading, paving, storm drain, water main & sewer work on the Technology High School campus in Rohnert Park.
Project Characteristics
Public Work
Original Contract Amount $2,954,589
Owner: Cotati-Rohnert Park Unified School District
General Contractor: Wright Contracting
Burge Building
Burge Building
The Burge project consists of demolition, grading, paving, storm drain & water main work for a new distillery in Rohnert Park
Project Characteristics
Private Work
Original Contract Amount: $228,400
Owner: Rental Center Properties
General Contractor: 5280 CM
PSTC Multi Purpose Building SRJC Windsor Campus
9/18-6/19


PSTC Multi Purpose Building SRJC Windsor Campus
The PSTC Multi Purpose Building project consists of demolition, grading, paving, storm drain, water main & sewer work on the SRJC Windsor campus for infrastructure to a new multi purpose building. The work also includes ADA improvements throughout the existing campus.
Project Characteristics
Public Work
Final Contract Amount: $408,400
Owner: Santa Rosa Jr. College
General Contractor: JL Modular/Construction
1111 Main St Helena
5/19-6/19
1111 Main St Helena
The 1111 Main Project consists of grading, paving and sewer work.
Project Characteristics
PrivateWork
Final Contract Amount: $70,800
General Contractor: 5280 CM
Golden State Cider
2/19-5/19


Golden State Cider
The Golden State Cider project consists demolition, grading, paving & electrical conduit work for their new manufacturing facility in Healdsburg.
Project Characteristics
PrivateWork
Final Contract Amount $77,800
Owner: Golden State Cider
General Contractor: Eddinger Enterprises
Montage Healdsburg
11/18-5/19

Montage Healdsburg
The Montage Healdsburg project consists of grading & erosion control work for the new resort in Healdsburg.
Project Characteristics
Private Work
Final Contract Amount $800,000
Owner: Montage Hotels & Resorts
General Contractor: Wright Contracting
Terrace Middle School
2/2018-2/2019


Terrace Middle School
The Terrace Middle School project consists of demolition, grading, paving, sewer & storm drain work for a new 7 new buildings & expansive decorative courtyard.
Project Characteristics
Public Work
Final Contract Amount: $871,427
Owner: Lakeport School District
General Contractor: FRC, Inc.
Healdsburg High School Track & Field Modernization
5/2018-10/2018


Healdsburg High School Track & Field Modernization
The Healdsburg High School project consists of demolition, grading, paving, storm drain, water main & sewer work on the Healdsburg High School campus.
Project Characteristics
Public Work
Final Contract Amount 1,809,000
Owner: Healdsburg Unified School District
General Contractor: FRC, Inc.
Caltrans 04-2Q9504
Emergency Culvert Replacement
9/2018-10/2018

Caltrans 04-2Q9504
The Caltrans 04-2Q9504 is an emergency project consisting of replacing a failed culvert and installing a headwall on Highway 1 near Olema.
Project Characteristics
Public Work
Original Contract Amount: $250,00
Owner: Caltrans
Engelke Construction Yard & Office
5/2018-12/2018


Engelke Construction Yard & Office
The Engelke Construction Yard & Office project consists of building our 6,000 SF office & shop along with parking for our employees and parking for our equipment. Our portion of the project is grading, paving, water, sewer, Stormtech system & storm drain installation.
Project Characteristics
Private Work
Owner: Jerry & Joanna Engelke
General: Eddinger Enterprises